CARPENTRY RESTORATION

deck after
deck before
fascia after
fascia before
fascia mid production
fascia mid production
window trim after
window trim mid production

ABOUT THIS PROJECT

Assessment: Due to gutter failure and extended water time on the north side of the home, 2 fascia boards were replaced right above the entryway. Lime identified rotten window trim boards on a few windows as the joints had been split resulting in water logged wood. The 2nd story deck also needed more than just a re-paint, it was identified that the horizontal railing was rotted due to its natural characteristic of being a water prone area. Lime replaced a few spindles and the horizontal railing with a composite PVC board so that moving forward this deck would resist it’s natural weathering patterns.